2013 - 2014 Madonna Expansion Project Overview

See the Catholic Voice article about our construction project.

We are expanding our physical plant in two phases.  As progress is made, we will update the following pages to reflect the developments. 

  1. Overview of the project's two phases
  2. Planning and design
  3. Preparing the site (moving the portable), June 2013
  4. Breaking ground on Phase I, July 22, 2013
  5. Digging the footings (Week of July 29, 2013)
  6. Pouring the footings (Week of July 29, 2013)
  7. Pouring the foundation (Week of July 29, 2013)
  8. Getting the walls up (Week of August 5, 2013)
  9. Preparing the Portable (Week of August 5, 2013)
  10. Laying the Underground Plumbing (Week of August 12, 2013)
  11. Pouring the Pad (Week of August 12, 2013)
  12. Interior Framing (Week of August 19, 2013)

 Subscribe to our Madonna Expansion Program email updates here:


 